Project Timeline
The Design phase typically takes 1-6 months. Most ADU projects take 12-18 months to complete, but some extend to 24 months or more.
Design FAQs
Here are a few of the most frequently asked questions about ADU design. See the content below and our ADU Guidebook for more guidance, resources, and tips for all steps of the process.
-
Most homeowners choose to work with some type of design professional to plan their ADU and help throughout the process. Bringing on a professional early in the process is often key to getting your ADU approved quickly, managed efficiently, and built cost-effectively. Relevant experience and fit will be critical.
There are a variety of types of designer, and they may be an architect, builder, “designer,” design/build, or a modular/prefab company. If you’re hiring a local individual or team, they’ll likely start the process by visiting your home and talking to you about your ideas and goals. If it seems like a good match, they will prepare a proposal detailing their services and fee. Professionals typically charge for an initial consultation or proposal.
Note that if you’re not using a licensed architect to design your ADU, your plans may need to be stamped by a licensed engineer. Check with local staff early on.
See our Exercises for a list of questions to ask a potential architect or designer, our Glossary to be clear on terms, and our Guidebook for more details.
-
Once you have a design established with your architect/designer, it’s a great idea to discuss it with local staff so they can point out any issues before you prepare your application.
Depending on the location, you may be able to schedule an appointment or you may be able to visit the Planning Counter or Permit Center. For contact information, see the Local ADU Rules.
This is also a good time to reach out to utility agencies (water, sewer, gas, etc.) to inquire about their infrastructural requirements and confirm connection and service fees.
-
Some locations may have pre-approved plans that applicants can customize for their properties. Currently Oakland and Fremont have pre-approved plans and more locations may be adding programs. Check Local ADU Rules to see if your location offers pre-approved or pre-reviewed plans.
Design Key Resources
These guides and resources are here for you as you get familiar with the process of building your dream ADU.
ADU GUIDEBOOK
A step-by-step guide to building an ADU in Alameda County.
FLOORPLANS
A gallery of real-world ADU floorplans.
stories
Explore why your neighbors are building ADUs!
Design
Once you have a sense of what you want to build, know what you can build, (Learn the Rules) and have estimated your budget (Budget), you can start designing your ADU, which begins with design inspiration and ends with permit-ready plans.
Before you begin …
It is helpful to have a clear sense of what you want early in the process. An architect or designer can help you brainstorm, but they cannot start designing until you’ve made basic decisions like the type of ADU you want (see Getting Started) and how many bedrooms it will have. Our Exercises can help you think about these questions.
Consider using a pre-approved plan
Check for local pre-approved ADU plans to give you a head start. Using an existing plan can save you time and money. Currently, Oakland and Fremont have pre-approved plans and more locations may be adding programs. Contact local staff to find out if there are pre-reviewed or permit-ready plans offered. It is also important to know that pre-approved plans still go through the permitting review process, however, if the plans are not changed, the permit process can take less time and potentially save you money too.
Hire experienced professionals
Although you can build an ADU as an owner-builder, we strongly recommend hiring a licensed architect or designer and a licensed contractor, or a design/build team, and most homeowners do. Bringing on a professional early in the process is often key to getting your ADU approved quickly, managed efficiently, and built cost-effectively. Relevant experience and fit are critical, and it’s important to look at their past work and check references.
Your team may include one or more of the following:
Licensed architect or designer to design your ADU and potentially see you through permitting and construction
Licensed contractor to build your ADU
Design/build company that designs and builds your ADU
Modular/prefab company who sells preset designs for modular/prefab homes
Our ADU Exercises include a list of questions to consider when hiring a team, and our Guidebook provides an overview on design contracts and costs.
Once you have your team in place, you will work with them to design your ADU. Together you will consider size, use, layout, specific project needs (storage, laundry room, etc.), architectural style, and privacy.
Once you have an initial design, it’s a good idea to discuss it with local staff so they can point out any issues before submitting your permit application. Your design team can attend this meeting to clarify drawings and help you understand requirements.
If you haven’t already, this is also a good time to reach out to utility service providers (water, sewer, gas, etc.) to confirm your design meets their requirements. See the Local ADU Rules and Contacts or the Directory in our Guidebook for all relevant contact information.
Create initial design
Finalize plan
Based on your meeting with staff, your team will work through any required changes and prepare the permit application (see Permitting).
Learn from others in your community
Renee and Debra, City of Alameda
“My mom was a great support when I became a single parent and we wanted to keep our family together so we bought a house and built an ADU. The ADU has increased our property value and we’re grateful for the flexibility to rent or host visiting family. Teaming up has been a great gift and we’re so glad we took this leap together.”
Keeping the generations together and thriving in Alameda (City)
Explore the design process in detail in our ADU Guidebook
Your go-to, in-depth guide to building an ADU in Alameda County, from inspiration to move-in.
← Back
Budget & Finance
Next →